Futures Housing and KLEG Offsite Build

INTRODUCTION

Futures Housing and KLEG Offsite Build worked together to arrange the movement and storage of modular Housing Units. Having assisted in a previous project, Merritts were assigned to carry out the moving and storage element of the works.

Merritts Modular Housing Move1Merritts Modular Housing Move1

PROJECT DETAILS

– An initial site visit was carried out to identify any possible hazards and to ascertain the lifting requirements for the project

– Method statement, risk assessments and bespoke lifting plans were produced for each lift

– Fencing was erected around the perimeter of the work area and the necessary signage displayed

– A MEWP was used to gain access to the roof of the modular buildings

– Operative harnesses were attached to a fall arrest block which was secured to an anchor point on the roof

– This allowed the Merritts operatives to safely attach the crane hooks from the mobile crane to the lifting eyes of the modules

LIFTING EQUIPMENT

– 80 Te Mobile Crane

-Versa-Lift 25/35

– Cherry Picker

– Rigging tackle

DISMANTLING AND LOADING

– Each home consisted of 4 modules (approx. 6Te each) bolted together. Prior to the lift, Merritts ensured that all modules were correctly unbolted from one another

– An 80Te Mobile crane was then used to lift the modules and slew acrossto Merritts’ awaiting low loaders

– Each module was safely lowered on to the deck of the trailer
– Merritts ensured the modules were suitably secured prior to transit

Merritts Modular Housing moving

TRANSPORT

Merritts provided multiple vehicles to ensure there was minimal downtime between each module collection.

A traffic regulation order (TRO) was arranged by the project team to ensure parking restrictions were in place in the vicinity of the works. This allowed suitable access for both the mobile crane and Merritts HGV’s.

Due to the width and height of the modules the transport element was a notifiable load movement. Merritts arranged this with the relevant authorities 3 weeks in advance of the works. A nominated route had to be followed and the drivers had an allocated 2 hour window in which they could operate.

All of the 16 modules were safely transported along the M1/A38 to Merritts site in Kirkby-in-Ashfield.

Merritts Modular Housing Move1

TESTIMONIAL

“Having worked with Merritts on a previous project they were an obvious choice to carry out this work. I was impressed with their professionalism from start to finish. Their health and safety team’s preliminary site visit ensured all hazards were identified and the necessary safety documents were produced. This gave peace of mind, especially as we were operating in a residential area. The storage service they provided was of an added benefit as we were allocated a dedicated area which we could have access to as and when required”.

Derick Wilson, KLEG Offsite Build

Request a Quote

Please leave a few details and a member of our team will be in touch to discuss your requirements in more detail.

Please upload any relevant images or files that will help us with your enquiry

Captcha (Please enter the characters as you see them)captcha

Enquiry

Please leave a few details and a member of our team will be in touch to discuss your requirements in more detail.

Please upload any relevant images or files that will help us with your enquiry

Captcha (Please enter the characters as you see them)captcha

Request Callback

Please leave your name and number and we will contact you shortly.

Captcha (Please enter the characters as you see them)captcha

Request a Brochure

Please select your brochure

Captcha (Please enter the characters as you see them)captcha